Hyundai plant: What you need to know about water, sewer infrastructure related to megasite

While the region looks ahead to the 2025 opening of the Hyundai plant, counties and development authorities are racing to install the necessary infrastructure before the South Korean car manufacturer can open its doors.

The 3,000-acre megasite, soon home to the state's first EV factory, is "raw," according to Trip Tollison, CEO of the Savannah Economic Development Authority. That means there's no water, no sewer, barely any power and no paved roads.

An example of a water treatment plant
An example of a water treatment plant

"But you don't get these massive facilities or small facilities without it," Tollison said of the necessary infrastructure. "So, you have to plan ahead. You have to get it in the ground. You got to test it. You got to design it, you got to construct it."

Hyundai plant: What you need to know about roads, bridges and traffic changes near megasite

Traffic in the middle of nowhere?: Residents near future Hyundai plant brace for road changes

Everything comes down to poo: Solving water and sewer issues key to attracting Hyundai

Commercial crush?: As Hyundai plant builds out, services and suppliers race to be close by

Hyundai fuels growth: What you need to know about businesses that will serve EV factory, employees

The plans to install water and sewer capacity on the site rely on cooperation between three counties, the creation of four new drinking water sources, and the construction of a new wastewater facility. And while the infrastructure improvements will help increase water and sewer capacity for the megasite, the upgrades will also serve as a short-term solution for the anticipated residential growth of northern Bryan County, seen in the construction of additional industrial parks and neighborhoods such as Heartwood, to be built about a 45-minute drive from the site near Richmond Hill.

The City of Savannah draws water from Abercorn Creek and treats it for drinking water.
The City of Savannah draws water from Abercorn Creek and treats it for drinking water.

Water and sewer are not as glamorous as 10,000-home subdivisions or $5 billion factories, but those utilities provide the necessary infrastructure for growth.

"These aren't fun things to talk about because everybody expects it. Nobody thinks about water and sewer because it's always a given," Tollison said. "But you can't expand communities, you can't expand even schools. You can't do anything without it."

To meet the future demand on water and sewer infrastructure from the megasite, the region is tackling expansion through two distinct projects. Here's a look at what they are.

Hyundai is constructing an 11-building, 16 million-square-foot EV assembly plant in rural Bryan County. The factory is to sit on a 3,000-acre site and is projected to employ 8,100 workers when it reaches full capacity. The opening date is January 2025, an aggressive timeline that speaks to the growing demand for electric vehicles. The schedule also puts a premium on developing infrastructure on and around the site.

This week, Savannah Morning News' journalists will explore the major infrastructure challenges ahead.

Tuesday: Roads, bridges and traffic-related issues

Today: Water and sewer

Thursday: Services and suppliers

New wastewater facility coming to Bryan County

Construction of a new wastewater treatment plant is underway in Bryan County. The facility is being built specifically to meet the needs of the megasite and the northern part of the county's growth.

The reclamation facility will sit on megasite property and include two new pump stations and a new "force main," or pressurized pipeline, that will carry waste east along the Interstate 16 corridor towards existing pump stations, according to the regional sewer plan submitted as part of the Hyundai deal.

The sewer infrastructure plan created for the Hyundai deal, which secured a $5 billion investment to bring an electric vehicle factory and 8,000 jobs to northern Bryan County
The sewer infrastructure plan created for the Hyundai deal, which secured a $5 billion investment to bring an electric vehicle factory and 8,000 jobs to northern Bryan County

"It's going to be a permanent regional wastewater facility that Bryan County will operate... this facility will accommodate long-term and short-term wastewater needs for not only north Bryan County, but it could serve southern and western Chatham and southeast Bulloch as well," Tollison said. "The sewer, it's a big deal for long-term success — and not just Hyundai, but the whole region."

The problem: Proposed Effingham industrial park threatens Abercorn Creek

The science behind it: Development risks regional drinking water supply

'Can't shut the gate after you come in': Residents in Bryan, Effingham counties wrestle with growth

Real estate: Longtime, prospective residents feel priced out of Bryan County

The Hyundai plant will discharge treated waste into the Ogeechee River, creating a point of concern for the Ogeechee Riverkeeper Damon Mullis, who is charged with protecting and advocating for the Ogeechee River and its watershed.

"We're obviously really concerned about just that point source," Mullis said.

The now-closed Milliken Plant upriver from the megasite had a similar permit to discharge waste into the Ogeechee River, which once caused a massive fish kill when chemicals were released into the water.

Bryan County put out a bid on the site in October 2021, with construction slated — and necessary — to be completed before the Hyundai plant's 2025 opening.

Aerial view of the Bryan County megasite.
Aerial view of the Bryan County megasite.

Four water wells to be dug in Bulloch County's 'green zone'

Drinking water is an obvious and necessary piece of infrastructure required for communities to grow. For the megasite, Tollison said four new wells are to be dug in southern Bulloch County specifically for the needs of the Hyundai plant.

The wells are in the upper Floridan aquifer's "green zone," meaning the water is abundant with no risk of saltwater intrusion. In parts of Chatham and Bryan counties, saltwater intrusion has rendered those sources in the yellow and red zones, meaning increased demand on the aquifer could worsen the already-salty waters.

The water infrastructure plan created for the Hyundai deal, which secured a $5 billion investment to bring an electric vehicle factory and 8,000 jobs to northern Bryan County
The water infrastructure plan created for the Hyundai deal, which secured a $5 billion investment to bring an electric vehicle factory and 8,000 jobs to northern Bryan County

By pulling from the green zone, Tollison said, the megasite's water source will remain stable.

But the solution isn't a cure-all for the long-term, regional needs for drinking water. It's meant to provide a "short-term solution" for the next two decades, Tollison explained.

"Ten to 20 years may seem like a long time, but this is sort of an interim solution while we really work to expand a surface water from the ID plant going west," Tollison said, referencing Savannah's water intake plant along Abercorn Creek.

A map of the Floridan Aquifer, the Georgia lowcountry's main source of groundwater.
A map of the Floridan Aquifer, the Georgia lowcountry's main source of groundwater.

Dozens of miles of new pipelines will be installed to carry water to the megasite from the wells in Bulloch County. Like the sewer improvements, the new water lines will need to be installed and operational by the time Hyundai comes online in three years.

Tollison said the temporary fixes will give leaders time to figure a long-term solution to water and sewer woes, including "weekly" conversations about expanding water resources with the city of Savannah.

"The next step is getting that surface water extended, because that absolutely has to happen for long-term growth."