$8.7M downtown Rock Island work to start April 16

The long-planned $8.7-million rebuilding plan for downtown Rock Island will start attacking the streets on Tuesday, April 16, 2024, with reconstruction expected to be done by December.

“We’re so excited for this project to happen, there’s no doubt about that,” Mayor Mike Thoms said Wednesday afternoon at a pre-construction update at The Stern Center, with representatives of the city, Rock Island Downtown Alliance, architects, engineers, general contractor, as well as businesses and residents.

Rock Island Mayor Mike Thoms introduces the meeting on the downtown reconstruction project, Wednesday, April 10, 2024 (photo by Jonathan Turner).
Rock Island Mayor Mike Thoms introduces the meeting on the downtown reconstruction project, Wednesday, April 10, 2024 (photo by Jonathan Turner).

“During the construction, it’s gonna be a bit of a pain, but the end result is going to be outstanding,” the mayor said, noting the downtown plans date back to 2015. “It’s the biggest investment that’s happened in many, many years,” Thoms said, noting one goal is to improve the downtown appearance to help attract businesses to fill empty buildings.

Jack Cullen, executive director of the Rock Island Downtown Alliance, said they started fundraising and putting plans together in spring 2021, and the general contractor will be Valley Construction of Rock Island.

Rock Island Downtown Alliance executive director Jack Cullen emphasizes the downtown business will stay open during construction, April to December 2024 (photo by Jonathan Turner).
Rock Island Downtown Alliance executive director Jack Cullen emphasizes the downtown business will stay open during construction, April to December 2024 (photo by Jonathan Turner).

Cullen reviewed the overview of project work. The three phases are:

  • Phase 1 – 18th Street from 1st to 3rd avenues; 3rd Avenue from 18th to 19th Street, and 2nd Avenue from 18th to 19th, to start April 16 and projected completion in November/December.

  • Phase 2 – Intersections of 19th Street and 2nd Avenue, and 19th and 3rd, to start in October, finished in December.

  • Phase 3 — Arts Alley reconstruction, in 1700 block of 2nd Avenue, starting in June, and finished in July.

New landscaping, lighting, welcome signage and arches will not be erected until spring 2025. Also in 2025, the city is planning to reduce 1st Avenue (Illinois 92) to one lane each direction and turn lane into downtown, as separate from the Rebuild downtown project, Cullen said.

The work includes complete reconstruction of streets, new sidewalks, new utilities (water and sewer lines), and streetscape improvements including streetlights, trees, benches, trash receptacles, public green space, gateway signage, and outdoor patios.

The planned roundabout in downtown Rock Island, 18th Street and 2nd Avenue.
The planned roundabout in downtown Rock Island, 18th Street and 2nd Avenue.

There will be a major gateway arch placed at 1st Avenue and 18th Street.

A new mini-roundabout will be put at the intersection of 18th and 2nd, to enhance pedestrian and vehicle safety, as well as “serve as this central focal point, symbolizing the true historic center of our downtown,” Cullen said.

There’s a new green space proposed for 2nd Avenue and 18th Street, to replace an existing parking lot next to the former Blue Cat Brew Pub. It will be a flexible, mixed-use space to be used by the community, Cullen said.

A planned new green space will replace a current parking lot near 18th Street and 2nd Avenue.
A planned new green space will replace a current parking lot near 18th Street and 2nd Avenue.

He emphasized that businesses will remain open during construction, and all the partners will work hard to keep everyone informed about the status of work. That includes inviting people to sign up for a bi-weekly e-newsletter, and holding monthly meetings with stakeholders throughout the process.

“Thank you in advance for your patience, collaboration and teamwork,” Cullen said. “That’s what public-private partnerships are all about.”

Jason McKenzie of the engineering firm Veenstra & Kim, spoke about making sure communications are clear, consistent and frequent among all affected parties. Construction work will primarily be weekdays from 7 a.m. to 3:30 p.m.

A map showing the two main phases (18th Street is within blue at left), with the first phase starting April 16, and the second in October.
A map showing the two main phases (18th Street is within blue at left), with the first phase starting April 16, and the second in October.

Aaron Lubitz of Valley Construction noted the first steps are demolition of existing streets, and work underground. “We got to get from low to high,” he said, adding that will take the first two months.

Available city-owned parking during construction will be:

  • City lot at 3rd Avenue between 17th 18th streets

  • City lot near bus station at 2nd Avenue and 19th

  • 2nd Avenue between 17th and 18th

  • West side of 19th Street between 1st and 2nd

  • South side of 2nd Avenue between 19th and 20th

  • 19th Street from 2nd to 3rd

  • North side of 3rd Avenue between 19th and 20th

  • City lot on southwest corner of 3rd and 17th

  • 18th Street between 3rd and 4th avenues

  • 19th Street between 3rd and 4th

The city and Downtown Alliance are working to get leases on future available parking owned by Modern Woodmen for their lots at 1st Avenue and 17th Street, and southeast corner of 2nd and 20th Street. These are not available now.

All improvements are to be completed by June 2025, Lubitz said.

Denny Hitchcock, owner of Circa ’21, asked if there will be a net loss of parking spaces with the project.

Lubitz said there will naturally be loss of on-street parking during construction, but they’re working to minimize impacts.

Hitchcock also asked if there will be financial assistance available to businesses for lost revenue because of construction.

Jack Cullen, right, listens as Aaron Lubitz of Valley Construction talks about the project Wednesday, April 10, 2024 at The Stern Center (photo by Jonathan Turner).
Jack Cullen, right, listens as Aaron Lubitz of Valley Construction talks about the project Wednesday, April 10, 2024 at The Stern Center (photo by Jonathan Turner).

“We are working with the city, talking about possible funds to help with business interruption, impacted businesses during construction of the project,” Cullen said. “We don’t have anything concrete, but we are exploring it. So stay tuned and hopefully we will be able to find some additional funds for that.”

McKenzie said work on rebuilding 2nd Avenue (including tearing out the pedestrian plaza for a new road and wider sidewalks) will be done first, but portions of 2nd and 3rd will be done together.

Picking Arts Alley artists

While not part of the Valley contract, the revitalization of Arts Alley, 1719 2nd Ave., will be done concurrently, including painting of huge new murals on each wall.

The current east-facing wall at Arts Alley, 1719 2nd Ave., Rock Island.
The current east-facing wall at Arts Alley, 1719 2nd Ave., Rock Island.

Quad City Arts received over 400 artist submissions from around the world to create two new outdoor murals at Arts Alley, next to its downtown Rock Island building. Representatives of the Rock Island Arts Commission and Downtown Alliance board narrowed down the potential artists to 10 finalists, based on their mural samples (including most recent completed), artist bio and work experience, Quad City Arts executive director Kevin Maynard said Thursday.

The west-facing wall of Arts Alley.
The west-facing wall of Arts Alley.

“It was incredibly difficult,” he said of picking finalists, who each will be paid $500 to submit specific Arts Alley designs by the end of the month. “We had over 400 submissions in the process – that’s up significantly from what we did in Moline.”

Quad City Arts expects to display the proposed 10 designs (including one from a local artist chosen) at their downtown gallery (1715 2nd Ave.), and one or two other downtown businesses, to collect public feedback.

They hope to make a selection of two artists (or teams) by early May and the murals done in June, Maynard said.

“It’s really hard. Even though we narrowed it down to 10, there are some really impressive artists that didn’t make that cut,” he said. “If we had an ample amount of money, we would be bringing even more artists in.”

A rendering of a revitalized Arts Alley, to be completed in July 2024.
A rendering of a revitalized Arts Alley, to be completed in July 2024.

The payments for the Arts Alley artists will be:

  • Mural 1: $33,600 (80 feet x 28 feet)

  • Mural 2: $27,000 (60’ x 30’)

Other improvements to Arts Alley (after murals are done) will include a decorative walkway, lighting and signage; space for social gatherings and performances; weatherproof vendor stalls for seasonal pop-up shop programs; and additional art installations.

You can see more renderings on all downtown improvements HERE.

For the latest news, weather, sports, and streaming video, head to WHBF - OurQuadCities.com.